Progress of construction works (09.08.2024)

One week has gone again and we can modify a little bit to do list, some works are done!

  1. Construction of the inside walls in two houses – 70% is done.
  2. Plastering, painting and wallpaper works in two houses: lime plaster done in main rooms, kitchens have to be finished. One main room painted, one to be done, wallpaper works to be done.
  3. Outside boarding: mainly done! (ten boards are missing, because material finished, we will get it).
  4. Gate work: needs to be completed: just work, not much new material needed. Roof of the gate done! Doors have to be done.
  5. Fence: most of the material bought, needs to be done. Help needed! Update: 08.08.2024: 300 meters of poles done, 100m of fence done (altogether it will be 500 meters. It is not 2 meters high and non trasnparent, but it works as a limit of the retreat center. Spruces that we planted last year, will grow soon and cover the view.
  6. Installation of 13 doors (3 exterior doors and 10 interior doors: 2000 euros). We can almost manage. Doors are on the way.
  7. Finishing the kitchen-storage room’s roof and ceiling, intallation of windows and a door. Windows and roof material almost there (some roof material needs to be bought. Lot of help needed. In front of the kitchen storage house a terrace has to be done to cover the part of the foundation we could not manage to build. These works have started.
  8. Kitchen windows for each house (5), installation of them. Little money and help necessary.
  9. Outside gardening works, excavator’s works where it could have not been done earlier. Some more flowerbeds done, other works not yet. (can be around 500 euros)
  10. Floor works (half og the material is there). Help needed.
  11. Assembly of IKEA kitchen furniture (arrived). Needs help from voluteers.
  12. Installation of the pump in the deep-drilled well (includes also the cost of the pump): 2500. Done by a company. Water is there! Finishing of the bathrooms (two not yet done at all) toilets and showers have to be bought (no money for that right now).
  13. Construction of wind boxes for houses, installation of gutters (no money for that work).
  14. Ceiling: heating material and installation (at least 1200 euros)
  15. Construction of stairways and a small terrace in front of each house (we start preparation works from tomorrow.
  16. Finishing of electricity works everywhere.